Type of plant:

HOKAWE Eberswalde

Customer:

Standardkessel GmbH

Project site:

Berlin

Project description:

Erection of the electrical and power engineering systems for the HOKAWE Eberswalde wood-fired power plant

Scope of services:

  • Hardware engineering, project engineering, CAD/CAE documentation with ELCAD,  manufacture, erection, cold and hot commissioning, trial operation

 

 Supplies:

  • 10.5 kV switchgears
  • Low-voltage switchgears 0.69 kV and 0.4 kV 
  • Auxiliaries transformer
  • UPS and direct current supply
  • Short-circuit and selectivity calculation
  • Main cable trays, local control points, cable storage
  • Grounding, potential balance

 

 Quantities:

  • 8 fields medium-voltage switchgears
  • 27 fields low-voltage switchgear system
  • approx. 2000 m main cable trays
  • approx. 35 km medium-/low-voltage cable

 

Technical highlights:

  • 10.5 kV switchgear system, Ik = 25 kA (1s) 1,600 A, withdrawable unit design made by Enertek,
  • Low-voltage switchgear 2,500A/1,600A, fixed installation with compensation, make: Enertek
  • 3200/1600/1600 kVA three-phase a.c. resin-encapsulated transformer, make: GBE S.R.L. (Italy)
  • UPS system 60 kVA with battery, 230/400V-UPS distribution, 220 VDC distribution, make: AEG